What Steps Do You Need For Valve Testing Equipment?

Oct 08, 2019 Leave a message

Valve viewing equipment is a must-have process, please see the process below:

1. Open the valve to check the power switch of the device, and the power indicator light is on.

2. Pay attention to whether there is any significant noise inside and outside the machine. If there is a suspension, ask the mechanic to determine if it is repaired.

3. Selecting the knife and loading the knife: It is operated by the designated personnel. Before loading the knife, it is necessary to compare the craftsmanship with the selected blade. If the tool is correct, the knife can be loaded. After the tool is completed, it is necessary to use the hand test. Check the power of the valve, press the touch button, use the special wrench to swing the main driven wheel, so that the hydraulic valve can check the stamping stroke of the equipment to the maximum. If the hand is not moving, then think about whether the pressure is too large or other questions, check the debugging to OK. . Before working, you need to check each locking screw and acknowledge that it is not loose.

4, loading: install the required terminal, use the hexagonal wrench to adjust the feeding plate, so that the terminal can easily pass, visual inspection of the feeding orientation is not appropriate, if not, conditioning, use the hexagonal wrench to loosen the feeder Tighten the screw, turn the conditioning mast to adjust it until the best condition, then lock the feeder locking screw and start working.

5, test pull: after adjusting the machine OK, take the waste wire to test, carry out the pull test, the primary reference value see the "pull test comparison table" specific operation

The method is as follows, press the pull test zero key to adjust to zero, clamp the terminal wire to be tested, and test, if the measured tension is not in the mark

Within the quasi-range, ask the mechanic to re-conditioning until the specification value is reached.

6, trial production 10PCS to send IPQC for the first piece of recognition, check OK, in order to mass production, the operator in the production process is necessary to self-test the terminal is not coated, hanging neck and other bad, and every 1 hour One terminal pull test.

7. Finish the good and waste products after the production is completed, and clean up the environmental sanitation around the machine.